how to include weekends in ms project

Mastering MS Project: How to Include Weekends in Your Schedule

By John Hernandez
AD

When it comes to project management, time is a critical resource. As such, it's essential to consider weekends and non-working days while scheduling tasks in Microsoft Project. Here, we'll guide you through the process of including weekends in Microsoft Project to ensure a comprehensive and accurate project plan.

To start, understanding that Microsoft Project considers only the weekdays (Monday to Friday) by default is crucial. However, with a few simple adjustments, you can incorporate weekends and make your schedule more realistic.

Working Days and Non-Working Days

First, let's define the working days and non-working days in your project's calendar.

AD
a screenshot of a project schedule with multiple tasks in the workflow diagram below
a screenshot of a project schedule with multiple tasks in the workflow diagram below
Microsoft to add Project features to its new unified Planner work management app
Microsoft to add Project features to its new unified Planner work management app
Microsoft Project progress | How to show progress lines [step by step]
Microsoft Project progress | How to show progress lines [step by step]

Working days are the days when your team members are available to work on tasks, while non-working days are the holidays, weekends, or any other days they're not available. By setting these accurately, you can ensure that your project timeline is both realistic and achievable.

Setting Working Days

To set the working days in Microsoft Project, you'll need to customize the calendar.

Top 5 Ways to Make the Most of Your Weekend - I'm Busy Being Awesome
Top 5 Ways to Make the Most of Your Weekend - I'm Busy Being Awesome
Microsoft project add Holidays - project calendar
Microsoft project add Holidays - project calendar

1. Click on "File" and then "Options".

2. In the "Project" tab, click on "Advanced", and then click on "Edit Calendar".

AD

3. In the "Calendar" dialog box, select the calendar you want to modify (usually "Standard" for most projects).

4. Click on "Working Time...". Here, you can set the working days of the week. Ensure that only the days your team works are marked as working days. Click "OK" when done.

Setting Non-Working Days

To set non-working days, you can follow a similar process.

AD

1. In the "Calendar" dialog box, click on "Exceptions" in the left pane.

2. Click on "Add exception...". Here, you can set specific days in the year as non-working days. For instance, if December 25th is a holiday in your region, you can add it as an exception.

3. Once you've set your exceptions, click "OK" to save your changes. Now, Microsoft Project will consider these dates as non-working days in your project's schedule.

AD

Understanding and Managing Resources

After setting the working and non-working days, it's crucial to understand how Microsoft Project manages resources during these periods.

Work.Account worked On is a field in Microsoft Project that determines when a resource can work. It defaults to working days, but you can set it to always work or never work, regardless of the calendar. This is particularly useful when you want to ensure that a specific task is completed on a particular day, even if it falls on a non-working day.

Setting Work.AccountWorkedOn

To set the Work.AccountWorkedOn field, follow these steps:

1. Select the task on which you want to work over the weekend.

2. Go to the "Advanced" tab in the "Task Information" dialog box.

3. Check the box next to "Work Accounted For On" if you want the resource to work even on non-working days. If you want the resource not to work on non-working days, uncheck the box.

Remember, setting this field will affect only the selected task. If you want to apply the same setting to all tasks, you might need to create a new calendar and apply it to all tasks.

By following these steps, you can effectively include weekends and other non-working days in your Microsoft Project schedule. This will not only make your schedule more realistic but also help you manage your resources more effectively.